METRO E Line construction update: August 29, 2025

Work is happening at these stations:

Dates are approximate and subject to change. As the construction season continues, crews may begin Saturday work at specific locations to maintain the overall project schedule. Future newsletter updates will include details where known.

University & Central, 4th Street & 6th Avenue, and University & 6th Avenue

  • Temporary E Line stations are being constructed at these locations. MnDOT will begin their reconstruction of University Avenue SE and 4th Street SE in 2027 at which time permanent E Line stations will be constructed at these locations. You can learn more about the project here.

Week of Sept. 2:

  • Crews will place traffic control and begin sawcutting and removal of concrete.

  • This work includes the use of heavy machinery, and impacts such as vibrations, loud noise, and dust and debris are to be expected.

  • Crews will work on underground utilities.

Week of Sept. 8:

  • Crews will work on underground utilities.

  • Crews will construct sidewalks.